DRENTH

BROTHERS INC.

SINCE 1948

                                                                       

 
 

 

2008 PRICE LIST
All material by the TON, Delivered prices for Tandems
  Cubic Yd   PER TON
Item CY PIT PRICE  Conversion   TON  Pit Price   DEL.-FULL LD Ton DEL.-PART LD. Ton Conversion
Beach sand $7.50 1.32 $5.70 $10.70 $13.20 1.32
Bank run gravel $6.00 1.50 $4.00 $9.00 $11.50 1.50
Processed Concrete Gravel Mix $10.85 1.50 $7.25 $12.25 $14.75 1.50
Processed Road Gravel 22A or 23A   $9.00 1.50 $6.00 $11.00 $13.50 1.50
Mortar Sand  2MS $12.10 1.32 $9.20 $14.20 $16.70 1.32
Concrete Sand - Washed - 2NS $7.75 1.32 $5.90 $10.90 $13.40 1.32
Ice Control Sand (1/4" max) $5.15 1.32 $3.90 $8.90 $11.40 1.32
Pea Stone (Washed 1/4" -- 7/16") $12.45 1.32 $9.45 $14.45 $16.95 1.32
Concrete Stone (Washed 7/16" - 1") $14.90 1.32 $11.30 $16.30 $18.80 1.32
Roofing & Landscape Stone (Washed 1" - 1 1/2") $14.90 1.32 $11.30 $16.30 $18.80 1.32
10A Drain Stone  (Washed 1/2" - 1 1/2")    $14.90 1.32 $11.30 $16.30 $18.80 1.32
6A Stone (Washed 1/4"- 1") $14.90 1.32 $11.30 $16.30 $18.80 1.32
29A 100% Crush 1/2"  (or 25A when aval.) $15.40 1.16 $13.30 $18.30 $20.80 1.16
6AA 100% Crush   (#4 - 1") $15.40 1.16 $13.20 $18.20 $20.70 1.16
Coarse Crusher Dust (Driveway Topping) $10.00 1.50 $6.70 $11.70 $14.20 1.50
Diamond Dust (Aglime from Kasson) $17.75 1.50 $11.85 $16.85 $19.35 1.50
Topsoil $11.00 1.11 $9.90 $14.90 $17.40 1.11
Screened Topsoil $15.00 1.11 $13.50 $18.50 $21.00 1.11
Fill Sand $2.35 1.50 $1.55 $6.55 $9.05 1.50
Fill Sand from Loeb Pit   CY Only 3.00 CY 1.50 3.00 CY $10.00 CY $12.00 CY 1.50
Fill Clay $4.40 1.50 $2.95 $7.95 $10.45 1.50
Filldirt/Topsoil Combination $7.80 1.50 $5.20 $10.20 $12.70 1.50
Natural Rock  (1" -- 3" unwashed) Potato stone $13.50 1.43 $9.45 $14.45 $16.95 1.43
Natural Rock  (4" -- 10" unwashed) $19.00 1.32 $14.40 $19.40 $21.90 1.32
Natural Rock  (8" -- 14") $28.50 1.32 $21.60 $26.60 $29.10 1.32
Natural Rock  (8" -- 24") $35.50 1.35 $26.30 $31.30 $33.80 1.35
Afton Road Mix $17.75 1.32 $13.45 $18.45 $20.95 1.32
21AA Natural from Hersha pit $9.90   $7.50 $12.90 $15.50 1.32
           
Loading Charge for less than 4 tons $5.00 $5.00 $5.00 per load    
Delivery Charge up to 10 miles for 13 tons $6.50 $5.00 $5.40 per ton    
Delivery Charge up to 10 miles for 6 to 12 tons. $8.50 $7.50 $8.00 per ton    
Delivery Charge per mile over 10 miles     $4.50 per mile    
Minimum Delivery 6 tons or $70 plus cost of material            
To convert to cubic yards, multiply by conversion factor.  This is a close approximate.
Delivery prices do not include any hand or machine leveling.
We reserve the right to quote special prices on large volumes.
Orders of 13 tons or more that must be delivered in smaller quantities than full load because of site access or by customer request will be charged the less than full load price.
A 5% discount will be allowed to recognized contractors on bills paid by the 15th of the following month.  There will be no discount allowed on specially quoted material.
The contractor discount will not be allowed to customers who have been placed on a cash basis because of past payment experience.
For off season loading while the pits are closed (app Nov 15 thru Apr 15) we reserve the right to charge extra for moving of snow and opening stockpiles, or to require minimum quantities of material to be purchased. 
We reserve the right to change prices at any time or add a delivery fuel surcharge.

 

 

                     "QUALITY PRODUCTS AND SERVICES FOR OVER 50 YEARS"

Home  Profile  Equipment  Catalog  Reclamation  Contact Us

                           Retail Yard  Excavation  Wood Products  Aggregates

 

CONVERSION TABLES

 

 

To convert C.Y. to Tons

MULTIPLY the number of C.Y. by the Conversion Rate for that specific material (see table below).

Example: To convert 9 C.Y. of road gravel to tons you would MULTIPLY 9 x 1.5 = 13.5 tons

Example: To convert 10 C.Y. of mortar sand to tons you would MULTIPLY 10 x 1.32 = 13.2 tons

To convert Tons to C.Y.

DIVIDE the number of tons by the Conversion Rate for that specific material (see table below).

Example: To convert 23.33 tons of road gravel to C.Y. you would DIVIDE 23.33 tons by 1.5 = 15.55 C.Y.

Example: To convert 15.54 tons of topsoil to C.Y. you would DIVIDE 15.54 tons by 1.11 = 14 C.Y.

Prices are converted by the same process.

To convert our C.Y. price to it’s equal price per ton:

DIVIDE the price per C.Y. by the Conversion Rate for the specific material (see table below).

Example: To convert road gravel at pit price of $10.50 C.Y. to it’s equal ton price DIVIDE $10.50 by 1.5 = $7.00 ton

Example:To convert mortar sand at pit price of $11.75 C.Y. to it’s equal ton price DIVIDE $11.75 by 1.32 = $8.90 ton

To convert our T